Project

General

Profile

News

EclaireXL: Delays

Added by foft over 7 years ago

We received an update from the PCB company. Unfortunately it wasn't to say 'shipping' as we'd hoped.

Instead they requested some more information for their machine setup, so apparently they have not started assembly yet as promised!

They now have the information they need so I trust they will start this without further delay.

EclaireXL: Parts arriving monday

Added by foft over 7 years ago

Sent on:9:04 amFrom:Eric Wu
hi Panos
THE COMPONENTS WILL COME HERE ON MONDAY
THEN START to fabricate
about 3-4days to ship out

EclaireXL: Sub PCB - ready

Added by admin over 7 years ago

SUB BOARD
Techonology Finished Finished Time
MI (Manufacture Instruction) 2017/3/30 23:25:07
Board Cutting 2017/3/31 6:11:23
Drill 2017/3/31 6:20:52
First Routing 2017/3/31 10:39:14
Plated Through Hole 2017/3/31 10:39:21
Circuit 2017/3/31 14:29:37
Etching 2017/4/1 3:37:24
AOI 2017/4/1 11:10:01
Solder Mask 2017/4/1 14:51:25
Silkscreen 2017/4/1 18:36:48
Surface Treatment 2017/4/1 19:46:38
Double Drilling 2017/4/1 20:59:12
Routing 2017/4/1 23:05:01
Testing 2017/4/2 14:41:13
Package 2017/4/2 15:14:39
Delivery Ready

EclaireXL: Main PCB - ready!

Added by admin over 7 years ago

Techonology Finished Finished Time
MI (Manufacture Instruction) 2017/4/1 21:45:19
Board Cutting 2017/4/1 21:56:23
Drill 2017/4/3 0:00:18
Inner Circuit 2017/4/2 8:42:02
Inner Etching 2017/4/2 10:53:08
Inner Laminating 2017/4/2 21:49:04
Plated Through Hole 2017/4/3 3:41:22
Circuit 2017/4/3 4:14:26
Etching 2017/4/3 9:47:36
AOI 2017/4/3 11:52:37
Solder Mask 2017/4/3 14:39:13
Silkscreen 2017/4/3 18:08:43
Surface Treatment 2017/4/4 1:33:02
Double Drilling 2017/4/4 2:15:31
Routing 2017/4/4 2:15:37
Testing 2017/4/4 9:55:08
Package 2017/4/5 9:17:10

(61-66/66)

Also available in: Atom