04/18/2017
- 10:19 PM Delays
- We received an update from the PCB company. Unfortunately it wasn't to say 'shipping' as we'd hoped.
Instead they...
04/07/2017
- 06:59 PM Parts arriving monday
- Sent on:9:04 amFrom:Eric Wu
hi Panos
THE COMPONENTS WILL COME HERE ON MONDAY
THEN START to fabricate
about 3-4day...
04/05/2017
- 09:46 PM Sub PCB - ready
- SUB BOARD
Techonology Finished Finished Time
MI (Manufacture Instruction) 2017/3/30 23:25:07
Board Cutting 2... - 09:09 PM Main PCB - ready!
- Techonology Finished Finished Time
MI (Manufacture Instruction) 2017/4/1 21:45:19
Board Cutting 2017/4/1 21:5...
04/04/2017
- 08:24 PM Board ordered
- We've ordered the boards from the PCB manufacturer!