Activity
From 03/25/2017 to 04/23/2017
04/18/2017
- FO 10:19 PM Delays
- We received an update from the PCB company. Unfortunately it wasn't to say 'shipping' as we'd hoped.
Instead they requested some more information for their machine setup, so apparently they have not started assembly yet as promised!
...
04/07/2017
- FO 06:59 PM Parts arriving monday
- Sent on:9:04 amFrom:Eric Wu
hi Panos
THE COMPONENTS WILL COME HERE ON MONDAY
THEN START to fabricate
about 3-4days to ship out
04/05/2017
- AD 09:46 PM Sub PCB - ready
- SUB BOARD
Techonology Finished Finished Time
MI (Manufacture Instruction) 2017/3/30 23:25:07
Board Cutting 2017/3/31 6:11:23
Drill 2017/3/31 6:20:52
First Routing 2017/3/31 10:39:14
Plated Through Hole 2017/3/31 10:3... - AD 09:09 PM Main PCB - ready!
- Techonology Finished Finished Time
MI (Manufacture Instruction) 2017/4/1 21:45:19
Board Cutting 2017/4/1 21:56:23
Drill 2017/4/3 0:00:18
Inner Circuit 2017/4/2 8:42:02
Inner Etching 2017/4/2 10:53:08
Inner Laminating...
04/04/2017
- AD 08:24 PM Board ordered
- We've ordered the boards from the PCB manufacturer!